If you're new here, you may want to subscribe to my RSS feed. Thanks for visiting! Mud guns are meant to provide supplemental or primary mixing in mud tanks depending on the number being used and the pit size. They are best used in tank corners to keep solids from settling and a mud agitator is placed in the tank center.
 Mud Gun
How to operate the mud gun?
A. Safty information
TURN OFF. LOCK OUT, and TAG OUT the electrical power supply to the pumps feeding the mud guns before servicing.
Inspect the unit regularly, and replace damaged or worn components only with parts supplied by the original equipment manufacturer.
Before entering a mud tank for any reason, the mud agitators should be locked out and tagged out.
B. General maintenance
1. Grease the swivel once a week. Add (2) shots of a multipurpose NLGI no 2 grease.
2. Visually inspect the mud gun assembly for any leaks, loose fittings once a week. Repair as required.
3. Inspect mud gun jet nozzle for excessive wear. The nozzle has a 5/8” bore when new. The nozzle should be changed when the bore is 7/8” or higher. This should be done once a month.
Once installation is complete, the unit can be started by turning the feed pump on. The direction of discharge may be modified to suit the operators requirements by rotating the swivel.
How to calculate the mud gun qty on a mud tank?
Continue reading »
written by GN solids Control
\\ tags: mud agitator, mud gun, mud tank, Solids control
Drilling engineering is a subset of petroleum engineering. Drilling engineers design and implement procedures to drill wells as safely and economically as possible.
 solids control
Exploration and petroleum engineering are the oil and gas industry’s two main sections. Petroleum engineering is a field of engineering related to the production of crude oil or natural gas.
Drilling engineers are in charge of the process of planning and drilling the wells. Their responsibilities include:
- Designing well programs to prevent blowouts
- Designing casing strings and cementing plans, directional drilling plans, drilling fluids programs, and drill string and drill bit programs.
- Specifying equipment, material and ratings and grades to be used in the drilling process.
- Providing technical support and audit during the drilling process.
- Performing cost estimates and analysis.
- Developing contracts with vendors.
Solids Control is one of the most important phases of the drilling process. The primary reason for using mechanical solids control equipment is to remove detrimental drilled solids from the mud system. Mechanical separation of drilled solids is achieved via screen separation(shale shaker, mud cleaner, desander, desilter) or accelerated g-force(decanter centrifuge). Continue reading »
written by GN solids Control
\\ tags: decanter centrifuge, desander, desilter, Drilling engineer, Drilling Engineering, mud cleaner, oil&gas drilling, petroleum engineering, shale shaker, Solids control
Simply speaking, mud cleaner is desander, desilter, shale shaker 3 in 1, sometimes people called it 3 in 1. For a four phase cleaning solids control system, mud cleaner can do the job for 2nd and 3rdphase cleaning of drilling fluids.
 mud cleaner
GN mud cleaner features:
1 standard design with various treating capacity, 500gpm, 1000gpm, 1500gpm
2 large shaker screen area to dry the solids and recycle more fluids
3 compact footprint, container shipping suitable
4 Easy maintenance, stainless steel valve on each hydrocyclone can make the replacement of cone easier, you do not need to stop whole machine.
MI-SWACO mud cleaner features:
Designed to handle the entire circulating volume to remove and dry solids while retaining premium base fluid. They are equally effective for both weighted and unweighted drilling-fluids.The hydrocyclones make the primary separation with underflow directed onto the shaker vibrating screen.
GN mud cleaner VS MI-SWACO mud cleaner
| Model |
GN
ZJ703-2S12N |
SWACO 2-12/6T4 combo |
GN
ZJ853-3S16N
|
SWACO 2-12/8T4 combo |
| Treating capacity |
1000GPM |
1000GPM |
1500GPM |
1200GPM |
| Desilter cone |
4” x 12ea |
4” x 12ea |
4” x 16ea |
4” x 16ea |
| Desander cone |
10”x2ea |
12”x2ea |
10”x3ea |
12”x2ea |
Continue reading »
written by GN solids Control
\\ tags: desander, desilter, drilling fluids, hydrocyclone, mi-swaco, mud cleaner, shaker screen, shale shaker, Solids control
GN has 3 complete of mud systemfor sale now. They are in stock in our Beijing Warehouse. Originally there are 5 sets of complete rig package for drilling site in Iraq, and we already shipped the 2 of them to Iraq. Because of the bad situation in Iraq, the project is delayed, we will sell the left 3 sets of mud system with 30% discount.
 mud system for sale
If you are interested, welcome to visit GN, we will show you the mud system in our yard.
Applications for the mud tanks:
1000HP/1500HP oil rig complete mud system with Derrick Solids Control or GN Solids Control Equipments.
Specifications of the Mud Tanks System
1 Mud tanks:
7x400BBL Mud Tank for one set
3 sets total capacity=8400BBL
Dimension(LxWxH):1200x2900x2300mm
Including Shaker Tank, suction tank, storage tanks, mixing tanks completed with agitators, mud guns, centrifugal pumps.
2 Solids control equipments for one set:
Option 1:
3x Linear Motion Shale Shaker Derrick FLC2000
1xVacuum Degasser Derrick 1200
1xMud Cleaner with 3x10inch desander and 16x4inch desilter, underflow linear motion shaker Derrick FLC2000
2xDecanter Centrifuge Derrick DE1000
Option 2:
3x Linear Motion Shale Shaker GNZS703
1xVacuum Degasser GNCQ270
1xMud Cleaner with 3x10inch desander and 16x4inch desilter, underflow linear motion shaker GNZJ703-3S16N
Continue reading »
written by GN solids Control
\\ tags: centrifugal pump, decanter centrifuge, derrick, desander, desilter, mud agitator, mud cleaner, mud system, mud tank, rig package, shale shaker, Solids control, vacuum degasser
The Drill cuttings Management solution is designed to help maximize compliance with the waste management hierarchy principles, as well as ensuring that local regulations and standards are complied with. Ultimately, disposal will be required in all cases, be it solids and / or liquids.
 drill cutting management solution
Drill cuttings management solution usually including but not limit to:
1 collection of drill cuttings
There are various ways to collect the drill cuttings from the solids control system( shale shaker, mud cleaner, decanter centrifuge). Firstly you need a cuttings blowing pump to blow the drill cuttings and waste produced by centrifuge from a collection place in the site to a drill waste storage tank or directly to a transferred truck or boat, they called it ”bulk tank”. Then Screw conveyors are used to transport drill cuttings and centrifuge waste from one location on the rig to another, probably to a vertical cutting dryer in the drilling waste management system.
2 Storage of drill cuttings
A Drilling Waste Container is to storage drill cutting, centrifuge waste and pit cleaning wastes generated during drilling operations. The drilling waste containers are typically transported to a treatment and disposal site for further processing.
After the drilling waste is treated by vertical cutting dryer, the cuttings will be collected by a small waste container and be transported to other place, the fluids are pumped to high speed decanter centrifuge for further process.
Continue reading »
written by GN solids Control
\\ tags: brazil, container, cutting dryer, decanter centrifuge, drill cutting, drilling waste, mud cleaner, screw conveyor, shale shaker, Solids control, solution, vertical cutting dryer
Workover is used to refer to any kind of oil well intervention involving invasive techniques, such as wireline, coiled tubing or snubbing. More specifically though, it will refer to the expensive process of pulling and replacing a completion.
 workover parts
Workover Rig is available for both onshore as well as offshore. Before any workover, the well must first be killed. Since workovers are long planned in advance, there would be much time to plan the well kill and so the reverse circulation would be common. The intense nature of this operation often requires no less than the capabilities of a drilling rig.
Workover parts may include the following parts basically:
Workover rig, Manifold, triplex mud pump, mud system, BOP, Top drives, Blow out preventers.
Workover mud system:
GN solids control produced workover mud system for 250HP, 350HP, 450HP, 550HP, 650HP,750HP workover rigs. They have been applied in more than 60 countries in the world. Some clients may get the mud system from rig package supplier. But a much sane choice is to buy the mud system separately from solid scontrol Continue reading »
written by GN solids Control
\\ tags: drilling, mud system, offshore, oil, onshore, parts, rig, rig package, Solids control, workover
Brandt HS-3400 centrifuge is used to process unweighted and weighted, water-based and oil based drilling fluids(mud). Here we made a comparison between Brandt HS-3400 centrifuge and GNLW363VFD centrifuge.
 GNLW363VFD decanter centrifuge
What is the difference and specs in common?
| Model |
Brandt HS-3400FEVSD |
GNLW363VFD centrifuge |
| length |
124in(3150mm) |
117inch(2970mm) |
| width |
69in(1753mm) |
59inch(1499mm) |
| height |
59inch(1499mm) |
68inch(1727mm) |
| Weight |
7606lb(3453kg) |
6613lb(3000kg) |
| Bowl diameter |
14inch(356mm) |
14inch(356mm) |
| Bowl length |
49.5in(1257mm) |
49.5in(1257mm) |
| Maximum bowl speed |
4000rpm |
3900rpm |
| Typecal bowl speed |
2900rpm |
2800rpm |
| Max processing capacity |
200gal/min(757lit/min) |
176gal/min |
| Drive type |
Variable frequency drive(VFD) |
Variable frequency drive(VFD) |
| Max G-force |
3180 |
3000 |
| Gear box ratio |
52:1 |
39:1 |
| Gear box type |
Two stage, planetary |
Two stage, planetary |
| Main drive motor |
40HP(30KW) |
40HP(30KW) |
| Back drive motor |
25HP(19KW) |
10HP(7.5KW) |
Continue reading »
written by GN solids Control
\\ tags: Brandt centrifuge, centrifuge bowl, decanter centrifuge, HS-3400, NOV Brandt, Solids control, VFD
Dredgingis an excavation activity or operation usually carried out at least partly underwater, in shallow seas or fresh water areas with the purpose of gathering up bottom sediments and disposing of them at a different location.
 dredging Slurry Separation System
A dredge is a device for scraping or sucking the seabed, used for dredging. A dredger is a ship or boat equipped with a dredge.
The process of dredging creates spoils (excess material), which are carried away from the dredged area. Dredging can produce materials for land reclamation or other purposes (usually construction-related).
As mentioned above, dredging will creates excess material, for example. Stones, sand, masses,cuttings, etc, For the purpose of environment protection, we need to separate the real trash and get the usable material for construction-related industry. GN dredging slurry separation system(also called dredging dewatering system) will be a good unit for such application. GN standard 1000gpm DSS system has been widely used for dredging.in domestic and abroad. If you need a 2000gpm DSS system,we suggest you to buy 2 sets of 1000gpm unit, it is convenient to ship it by container and truck on the road.
1000gpm DSS: total power 130KW
Continue reading »
written by GN solids Control
\\ tags: 1000gpm dredging, dredge, dredger, dredging slurry separation system, m DSS, Solids control
GN new products hi-G dryer GNZS85-3 is designed to replace the old model hi-G dryer GNZS63-4. GN Hi-G dryer shaker is with long shaker deck big capacity which is used for waste management to treat the drilling cuttings from the primary solids control equipments, like shale shaker, desander, desilter to dry the solids for transportation, and make the fluids easier for future treatment. To know more info of primary solids control equipments, pls check GN website.
 GN hi-G dryer
What is the features of GNZS853 compared with GNZS63-4?
1 Even it is 3 –panel hi-G dryer, its screen area is larger than 4-panel hi-G dryer. The larger the screen area is, the dryer the cutting is. Total deck screen length is 2550mm, the total deck screen length of GNZS63-4 is 2520mm. Total screen area of GNZS85-3 is 3.2m2, but the total screen area of GNZS63-4 is only 3.15m2. And GNZS85-3’s screen area and total deck length is larger than Derrick 4-panle shale shaker/mud cleaner.
So 4-panel shaker is not must be better than 3-panel shaker.
2 3-panel shaker screen can enlarge the effective screen area, the waste screen area is less compared with 4 screen panel. It can improve the performance of hi-G dryer.
3 Mechanical deck adjustable while operation for reliable performance.
Continue reading »
written by GN solids Control
\\ tags: desander, desilter, drilling waste management, hi-G dryer, hi-G shaker, shaker screen, shale shaker, Solids control
Oil Well Choke & Kill Manifold are a kind of well-control equipments, GN solids control do not produce such equipments, our products range including a complete set of solids control equipments and mud tanks.
An arrangement of piping or valves designed to control, distribute and often monitor fluid flow. Manifolds are often configured for specific functions, such as a choke manifold used in well-control operations and a squeeze manifold used in squeeze-cementing work. In each case, the functional requirements of the operation have been addressed in the configuration of the manifold and the degree of control and instrumentation required.
Oil well choke manifold is high-pressure pipe leading from an outlet on the BOP stack to the backpressure choke and associated manifold. During well-control operations, the fluid under pressure in the wellbore flows out of the well through the choke line to the choke, reducing the fluid pressure to atmospheric pressure. In floating offshore operations, the choke and kill lines exit the subsea BOP stack and then run along the outside of the drilling riser to the surface.
A choke manifold is used to lower the pressure from the well head. It consists of a set of high pressure valves and at least two chokes. These chokes can be fixed or adjustable or a mix of both. The redundancy is needed so that if one choke has to be taken out of service, the flow can be directed through another one. these long choke and kill lines must be considered to control the well properly.
Continue reading »
written by GN solids Control
\\ tags: kill manifold, oil well manifold, Solids control, solids ocntrol equipments. choke manifold, well control equipments
|