GN customized mud system for Africa Drilling Client

The client is local drilling client for HDD project. The client is providing water well drilling contract to government companies, government oil drilling companies etc. Last year in Feb, 2015, the client bought two sets mud cleaning system. Each set mud system only with one mud recycling tank, mounting with one set shale shaker & one set mud cleaner.

Recently, the client is requiring one more compact mud system for water well drilling, 500gpm system with two tanks. One shaker tank is with shale shaker and mud cleaner, one mud mixing tank with agitators or centrifugal pumps.

 

Simple introduction of GN 500gpm mud system as below.

One shale shaker mud tank system including: one set shale shaker, one set mud cleaner, two sets centrifugal pumps. The shale shaker is GN patent 3 panel shale shaker, which have over 5 years jobsite experience. The shaker can work well in different hard conditions. The mud cleaner is GN 3 panel mud cleaner with GN compact design, down deck shaker and desilter cones. Another tank is mud mixing tank with mud agitators, mud guns and mud hopper for chemical mixing.

Except for this mud system, GN drilling waste management equipment is also very popular in the world.

Waste management centrifuge: GN decanter centrifuge is working after replacing USA brand centrifuges. The centrifuge can work for solids control, waste management, waste water treatment ect.  In solids control application, 2500rpm is generally used for mud weight cutting, and 1800rpm to 2000rpm is generally used for barite recovery.  In drilling waste management, 2500rpm to 3000rpm is generally used for removal the fine solids. In waste water treatment, higher speed centrifuge is required after chemical enhancement.

Vertical cuttings dryer is also called VG dryer, VG dryer can treat the drilling cuttings discharged from shale shaker, the OOC after VG dryer can reduce to about 3% to 5%, and the dry solids can be collected by cuttings skips and transport by trucks to a cuttings center for final treatment.

GN will attend CIPPE & OTC in the coming two months

GN Solids Control is attending CIPPE 2016 Beijing oil show at 29 to 31, March. We welcome clients from overseas to visit GN booth and talk more business cooperation. If client miss CIPPE oil show, we also have OTC USA oil show in May and Iran oil show in May. The client can also visit GN boot in USA or Iran which is close to client. The equipment is almost same, we will take the high technology solids control equipment to the exhibition and show the good product and talk more business with clients from different countries.

gn-cippe-2015 2

 

 

 1) Decanter centrifuge
Continue reading “GN will attend CIPPE & OTC in the coming two months”

GN 500gpm Mud System working for Water Well Drilling

GN Solids Control got repeated 5 sets 500gpm Mud System working for Water Well Drilling in Middle East. The client is local strong contract company having good relations with Local government. We arrange our engineer to Middle East jobsite for the first time mud system commissioning and the client is very familiar with the working process and maintenance and no need our coming in next 4 sets mud systems.

500gpm mud system for water well drilling

The mud system is equipped with below items.

1) Shale shaker GNZS703E-DZ

The shaker is GN mature shaker model which is used for over 5 years. Stable working performance and good price win the client’s good praise in past jobsite. The shale shaker is 3 panel shakers which is enough for Water well drilling or HDD project. If the client needs the long deck shaker with 4 panel screen, we can provide GNZS594E-HB shaker with replacement screen for Swaco Mongoose screen, both composite material and carbon steel material screen available.

Continue reading “GN 500gpm Mud System working for Water Well Drilling”